HomeMy WebLinkAbout2000-004 Urban Renewal Area Boundaries RESOLUTION NO. 4-2000
A RESOLUTION OF THE MAYOR AND COUNCIL OF THE CITY OF
CHUBBUCK, AMENDING RESOLUTION NO. 4-92, RESOLUTION 7-92,
RESOLUTION NO. 11-92 AND RESOLUTION NO. 4-95 AND
RESOLUTION NO. 4-96 TO DEFINE THE GEOGRAPHIC BOUNDARIES
OF THE URBAN RENEWAL AREA AND AMEND THE PLAN TO
INCLUDE ADDITIONAL PROJECTS.
Whereas, Resolution No. 4-92 declared the need for and created an Urban Renewal Area;
and
Whereas, Resolution No. 7-92 established the property lying within the Urban Renewal
Area; and
Whereas, Resolution No. 11-92 deleted the northern portion of the urban renewal area as
established by Resolution No. 7-92; and
Whereas, Resolution No. 4-95 and Resolution No. 4-96 added the city parks to the Urban
Renewal Area; and
Whereas, the Public Hearing conducted by the City of Chubbuck on, March 28, 2000
demonstrated the need to add to the Urban Renewal Area new City parks and add
construction projects to the original plan;
NOW TItEREFORE, be it resolved by the Mayor and the City of Chubbuck:
The property lying within and including the area legally described on the attached Exhibit
"A" be added to the existing Urban Renewal Area and Revenue Allocation District created
by Resolution No. 4-92 and amended by Resolution No. 4-95 & No. 4-96 and the
project construction elements identified on the attached Exhibit "B" be added to the Urban
Renewal Plan adopted in 1992.
Passed and approved by the Mayor and Council of the City of Chubbuck this 28 day of
March, 2000.
CITY OF CHUBBUCK
a municipal corporation of Idaho
ATTEST:
Ron Conlin, Clerk
EXHIBIT "A"
Description of parks to be included in the geographic area of the Urban Renewal District
Mary l~arker Park - additional land - Lot 2 Blk 11, Heights Subdivision
Vera Armstrong Park - additional land - Lot 10 Blk 5, Heights Subdivision
Capell Park o Lot 13 Blk 1, Diamond Court Subdivision
Jordons' Park - Lots 1,2,3 and 4 of Block 1 and Lot 1, Block 2 of Jordan's Park Subdivision
Bistline Park Extension - Bistline Park Lot, Block 1 of Hiline Heights Subdivision.
Exhibit "B"
REVISED COST ESTIMATES FOR CITY OF CHUBBUCK
URBAN RENEWAL CONSTRUCTION PROJECTS
March 28, 2000
Pine Ridge Mall Waterline Connection from Yellowstone Ave. to Hawthorne Rd.
16" Ductile Iron Waterline- 2,950 1.f. $45/1.f. $132,750.00
16" mainline vales- 8 $1,000/ea. $ 8,000.00
Landscape-7,500 s.f. $2/s.f.. $ '15,000.00
Pavement Repair - 350 sq. yd. $15/s.y. $ 5,250.00
Total $161,000.00
Bluebird Drive (Hiline Canal Crossing)
Precast Box Culverts - 60 $750/ea. $45,000.00
Precast Wing Walls - 4 $2,500/ea. $10,000.00
Cast in Place Concrete Parapet 20 1.f. $162/1.f. $ 3,240.00
Roadway Section- 40 s.y.. $15/s.y. $ 600.00
Standard Curb and Gutter- 20 1.f. $8/1.f. $ 160.00
4' sidewalk- 80 s.f.. $3.25/s.f. $ 260.00
Total $59,260.00
Burley DriVe ( Chubbuck Rd. to Burnside Ave.)
16" Ductile Iron Waterline- 3,526 l.f. $45/1.I~ $158,670.00
16" Mainline Valves - 7 $1,000/ea. $ 7,000.00
Ribbon Curb - 7,254 1.f. $8/1.f. $ 58,032.00
4' Sidewalk - 29,016 s.£ $3.25/s.f. $ 94,302.00
Roadway Section- 9,672 s.y.. $15/s.y. $145,080.00
Excavation - 3,000 c.y. $10/c.y. $ 30,000.00
Total $493,084.00
East Chubbuck Rd. (Buffalo Rd. to East City Limits)
12" C-909 PVC Waterline - 1,420 1.f. $30/1.~: $ 42,600.00
Storm Sewer System (Drywells) - 6 $2,500/ea. $15,000.00
Standard Curb & Gutter - 3,300 1.f. $8.00/1.f. $ 26,400.00
5' Sidewalk - 13,200 s.f. $3.25/s.f. $ 42,900.00
Roadway Section - 8,433 s.y. $15/s.y. $126,495.00
Excavation - 2,811 c.y. $10/c.y. $ 28,110.00
Total $281,505.00
Hawthorne Rd. (Chubbuck Rd. to Quinn Rd.)
Storm Sewer System (Drywells) - 22 $2,500/ea. $ 55,000.00
Standard Curb & Gutter - 10,700 1.f. $8/1.f. $ 85,600.00
5' Sidewalk- 53,500 s.f. $3.25/s.f. $173,875.00
Roadway Section - 36,261 s.y. $15/s.y. $543,915.00
Excavation - 10,700 c.y. $10/c.y. $107,000.00
Total $965,390.00
Hiline Rd. (Chubbuck Rd, to 1-86)
16" Ductile Iron Waterline - 2,700 1.f. $45/1.f. $121,500.00
16" Mainline Valves - 6 $1,000/ea. $ 6,000.00
Fire Hydrants - 6 $2,000/ea. $ 12,000.00
8" Sanitary Sewer Line - 430 1.f. $16/1.f. $ 6,880.00
Sanitary Sewer Manhole - 1 $1,500/ea. $ 1,500.00
Storm Sewer System (Drywells)- 12 $2,500/ea $ 30,000.00
Standard Curb & Gutter - 5,4001.f. $8/1.f. $ 43,200.00
5' Sidewalk - 27,000 s.f. $3.25/s.f. $ 87,750.00
Roadway Section - 18,300 s.y. $15/s.y. $274,500.00
Excavation - 5,400 c.y. $10/c.y. $ 54,000.00
Total $637,330.00
Capell Park
A. Underground
6" C-909 Waterline - 800 1.f. $17/1.f. $13,600.00
6" Mainline Valves - 2 $500/ea. $1,000.00
Fire Hydrants - 2 $2,000/ea. $ 4,00000
8" Samtary Sewer Line - 800 1.f. $16/1.f. $12,800.00
Sanitary Sewer Manhole - 3 $1,500/ea. $ 4,500.00
Total $35,900.00
B. Access
Ribbon Curb - 2,460 1.f. $8/1.f. $19,680.00
4' Sidewalk - 4,920 s.f. $3.25/s.f. $15,990.00
Roadway Section- 3,553 s.y. $15/s.y. $53,295.00
Excavation - 800 c.y. $10/c.y. $ 8,000.00
Total $96,965.00
C. Parking
Parking lot Section - 5,470 s.y. $15/s.y. $82,050.00
Excavation - 1,200 c.y. $10/c.y. $12,000.00
Total $94,050.00
D. Imgation
Materials - 17.31 acres $1,958/acre $33,892.98
Labor - 17.31 acres $1,788/acre $30,950.28
Total $64,843.26
Total cost of Park $291,758.26
Fire Station Addition
Construction of addition to fire station Total $40,000.00
Total of all projects listed $2,929,327.26