To: Honorable Mayor and City Council
From: Bridger Morrison
Date: March 9, 2023
Re: Sanitation Parking Building Re -Bid — Bid Award
Public Works Department
290 E. Linden Avenue, Chubbuck, ID 83202
208.237.2430 — Fax 208.237.2409
www.CityofChubbuck.us
In an effort to protect the vehicles and equipment and reduce maintenance expenses, the Sanitation
Department would like to have two parking buildings built at the maintenance yard. To keep costs as
low as possible, the buildings are intended to be simple buildings with metal roofs and siding on three
sides as shown in the attached figures. This project was included in the department's capital plan and
budget for this year. We bid this project first back in November 2022 and received a low bid of
$585,335. After discussing options with contractors, we made some changes to the plan and re -bid the
project this month. The City received one bid which is summarized below:
Contractor Building 1 (23 Bays)
Bid Amount
Building 2 (7 Bays)
Bid Amount
Total Bid for Both
Buildings
RS Jobber, Inc. $ 312,363.00
$ 89,447.00
$ 401,810.00
The City's budget for the buildings was $275,000, however, it appears we may be able to cover the extra
cost within the existing overall budget since some expenses are on track to be under budget. If the
project is awarded and it appears the Sanitation Department may exceed its budget later in the year, we
will need to make a separate request of the Council to open the budget and utilize additional reserves.
The bid appears to be responsive and meets the requirements of the bid documents. It is my
recommendation that the City Council approve the Mayor to execute a contract with RS Jobber, Inc. in
the amount of $401,810.00 for the construction of both buildings.
Sincerely,
Bridger Morrison, P.E.
Interim Public Works Director
PjSanitation�Projects�Yard Lean-to�Sanitation Award Recommendation-CounciLdocx
FRONT ELEVATION
12
1
LEFT ELEVATION
12
RIGHT ELEVATION
REAR ELEVATION
**PROPOSED SANITATION PARKING BUILDINGS**
BUILDING 1 - 23 OPEN PARKING BAYS FACING NORTH
WITH A MINIMUM HORIZONTAL CLEARANCE (COLUMN TO
COLUMN) SHALL BE NO LESS THAN 12 FEET. THE
VERTICAL CLEARANCE FROM FINISHED GRADE TO
BOTTOM OF HEADER SHALL BE NO LESS THAN 14 FEET.
BUILDING 2 - 7 OPEN PARKING BAYS FACING NORTH
WITH A MINIMUM HORIZONTAL CLEARANCE (COLUMN TO
COLUMN) SHALL BE NO LESS THAN 12 FEET. THE
VERTICAL CLEARANCE FROM FINISHED GRADE TO
BOTTOM OF HEADER SHALL BE NO LESS THAN 14 FEET.
DURING CONSTRUCTION
EXISTING ------,___.,MAINTAIN EAST/ WEST TRAVEL --
6" WATERLINE LANE FOR HEAVY EQUIPMENT
RETAIN AND PROTECT
fi" W 6" w 6" W 6" W
APPROX. 92'
xo' BUILDING 2 APPROX. 300'
*PROPOSED SANITATION
a PARKING BUILDING**
0 BUILDING 1 °
x _� a **PROPOSED SANITATION PARKING BUILDING**
+ a
-oo x x x x x x� x x� x
rx TT
x EXISTING _� EXISTING
FENCE RETAIN FENCE RETAIN J
AND PROTECT AND PROTECT
EXISTING Y x
6" WATERLINE
RETAIN AND PROTECT
HIGHWAYAVE.
-i
0 30' 60'
NO. DATE DESCRIPTION CITY OF CHUBBUCK D D. KENNEDY Its—
DWS .nrLE. PUBLIC WORKS OPERATIONS
-CONFIDENTIAL DOCUMENT- w DE SANITATION PARKING BUILDING HORIZ. SCALE: 1" = 60'
z
This drawing may not be reproduced or disclosed or 0 290 E. Linden Ave, Chubbuck, Idaho 83202 D. KENNEDY P 175 PARK LAWN DRIVE
used to construct or fabricate items shown on this N Voice: (208)237-2430 CHECKED BY:
drawing without the prior written permission of w CHUBBUCK Fax: (208)237-2409 cAPPRovA� CHUBBUCK IDAHO
CITY OF CHUBBUCK, IDAHO ENGINEERING DEPT. DWG. NAME: J:;60 1lSCALE: 1:60 sward Lean._tDesHEE 2 O Yard.tlwg
I I I N O Website: http//www.cityofchubbuck.usl
AHC APPRovAi. or SCALE: 1:6o SCALE: tso SHEET20F2