HomeMy WebLinkAboutItem #4 Philbin Chubbuck Roundabout/6470-t-\ CHUBBUCK 1 0 0 H 0 Memo To: Honorable Mayor and City Council From: Bridger Morrison Date: July 15, 2022 Public Works Department 290 E. Linden Ave., Chubbuck, ID 83202 208.237.2430 — Fax 208.237.2409 www.CityofChubbuck.us Re: Philbin Road / Chubbuck Road Roundabout — Change Order 1 Two recent changes have been required for the roadway contract for the Philbin Road / Chubbuck Road Roundabout Project: 1) At the request of the City, the contractor purchased a concrete irrigation box that was called out to be provided by the City. 2) The City requested that some additional sleeves be installed for future irrigation lines to serve the island and other areas. The proposed change order is for $11,286.00. The proposed change order form is attached. I am requesting the Council approve Change Order 1 for the Philbin Road / Chubbuck Road Roundabout project in the amount of $11,286.00. J:lAdministration�Director�Memos to Council�Philbin Chubbuck Roundabout C01 Memo to Council7-15-22.docx Change Order No. 1 Date of Issuance: 7/12/2022 Effective Date: 7/12/2022 Project: Philbin Rd / Chubbuck Owner: City of Chubbuck Owner's Contract No.: RFB 2022-03-10 Rd Roundabout Contract: RFB 2022-03-10 Date of Contract: 3/29/2022 Contractor: Mickelsen Construction Engineer's Project No.: RFB 2022-03-10 The Contract Documents are modified as follows upon execution of this Change Order: Description: A) Installation of irrigation box per sheet 9 of the construction plans. This wasn't included as a bid item on the contract documents. ($3,386.00) B) Installation of 3" irrigation sleeves following revision I of the landscape drawings provided from Jackson Land Design. ($7,900.00) Attachments (list documents supporting change): See attached documents CHANGE IN CONTRACT PRICE: CHANGE 1N CONTRACT TIM Original Contract Price: Original Contract Times: ❑ Working days ❑ Calendar days Substantial completion (days or date): $1,880,681.20 Ready for final payment (days or date): Increase from previously approved Change Orders Increase from previously approved Change Orders No. 0 to No. 1: No. 0 to No. 1: $0.00 Contract Price prior to this Change Order: $1,880,681.20 Increase of this Change Order: $11,286.00 Contract Price incorporating this Change Order: $1,891,967.20 RECOMMENDED: By: Engineer (Authorized Signature) Name: Print Name Date: Substantial completion (days): 0 Ready for final payment (days): 0 Contract Times prior to this Change Order: Substantial completion (days or date): Ready for final payment (days or date): Increase of this Change Order: Substantial completion (days or date): Ready for final payment (days or date): Contract Times with all approved Change Orders: Substantial completion (days or date): Ready for final payment (days or date): ACCEPTED: By: Owner (Authorized Signature) Name: Print Name Date: Approved by Funding Agency (if applicable): 2010 ISPWC 00941- Modified From EJCDC C-941 Change Order Page 1 of 1 ACCEPTED: By: Contractor (Authorized Signature) Name: Date: Date: Print Name