HomeMy WebLinkAboutARS Flood and Fire Cleanup MinutesOffice of Community Planning & Economic Development
PO Box 5604 – 5160 Yellowstone Avenue, Chubbuck, ID 83202
208.237.2430 – Fax 208.237.2409
www.CityofChubbuck.us
Design Review Committee Review via email
March 19, 2020
Applicant: ARS Flood and Fire Cleanup
Proposed site address: 5023 Rainbow Ln.
Emailed: Kevin England, Mayor; Rodney Burch, Public Works Director; Devin Hillam, Community Planning and Economic Development Director; Bridger Morrison, City Engineer; Bill Guiberson,
Police Chief; Merlin Miller, Fire Marshal; Don Matson, Senior Planner; Paul Andrus, City Planner; Ron Osborn, Building Official; Tom Holmes, City Attorney; Josh Packer, Pre-Treatment
Coordinator; Jason Mendenhall, Land Use Chairman; Derek Kennedy, Eng. Tech; Sean Harris Eng. Tech Kami Morrison, Office Administrator.
The project is a site plan review for a new 66 ft. by 76 ft. building on the rear of the ½ acre property. This is not a full review as it is only to add a building. It was done by Email
because of the Precautions instituted for the Covid 19 protocols. Meeting was scheduled for 9:00 am canceled at 8:50 am. after Mayors meeting with staff. Review was done individually
and reported via Email.
PROJECT REQUIREMENTS
TRAFFIC SAFETY AND TRAFFIC CONGESTION: No additional traffic expected.
TRAFFIC STUDIES, UTILITY STUDIES: No concerns.
OUTDOOR ADVERTISING:
Will need to submit a sign application review if signage is needed.
LANDSCAPING:
5% of the paved area needs to be landscaped. A 10’ landscaping strip is required on the street frontage of Rainbow.
Restore landscaping and 2 trees on Rainbow with an irrigation system for the landscaping requirement per 18.14 of City Code and Approved Tree list.
STRUCTURES AND SITE LAYOUT:
There presently is a building the will be used for an office.
There will be a 66 ft. by 76 ft. building added with no plumbing, stick built, insulated with metal siding.
Building plans need to go to the building Dept.
DRAINAGE: Storm water plans submitted to Eng. and Approved
PRETREATMENT: N/A
EXTERIOR LIGHTING: Lighting needs to be shielded to prevent light trespass.
ENGINEERING:
Storm water plans have been reviewed, no new utilities or infustructure
FIRE DEPARTMENT:
Knox box will be required and a visible street address.
BUILDING DEPARTMENT:
Submit plans and follow required setbacks
POLICE DEPARTMENT:
No Concerns
NONRESIDENTIAL WASTEWATER PERMIT: N/A
BUSINESS LICENSE: Need to apply for a business license before operating in Chubbuck
DEVELOPMENT AGREEMENT: N/A
Information was e-mailed to the Design Review Committee and applicant on March 19, 2020.