DESIGN REVIEW COMMITTEE MEETING MINUTES
September 24, 1996
DESIGN REVIEW SUBJECT: Harris Construction
DATE: September 24, 1996
APPLICANT: Harris Construction, 4555 Burley Drive.
PROJECT: Construction Office at 4555 Burley Drive.
Present: Mayor John 0. Cotant, Attorney Holmes, Steve Smart, Cary
Campbell, Ron Conlin, Kent Kearns, Larry Kohntopp, Jim
Phelps and Charlie Dickman.
Mr. Harris, Harris Construction presented a site plan for
construction offices at 4555 Burley Drive.
BI Cary Campbell explained to Harris Construction the 10'
landscaping, curb, gutter and sidewalk requirements.
Harris Construction was told they are required to sprinkle
the 10' landscaping area.
BI Campbell stated the plan should identify whether or not, Evans
Lane is on part of the site plan, if so Harris Construction
needs to understand where the street will 909 when
constructed.
BI Campbell stated, if an Local Improvement District is created on
the Property, that will take care of the curb, gutter and
sidewalk requirement.
PWD Smart stated the curb cut should be 20' from South Burley, with
a 30' approach.
Harris Construction asked PWD Smart to help find the surveyor pins.
PWD Smart said he will.
Discussion about Harris Construction platting the Property. At this
time the Property is not Platted, the Property is required to
be platted prior to any building permits issued.