HomeMy WebLinkAboutDR Todd's Auto 01 Apr 17 (2)DESIGN REVIEW COMMITTEE MINUTES
April 17th, 2001
DESIGN REVIEW SUBJECT:
Todd's Automotive, 5048 Rainbow Lane, Chubbuck.
DATE: April 17th, 2001
APPLICANT:
Todd Stinger/Tom Gwinn
PROJECT TITLE:
Todd Automotive, 5048 Rainbow Lane, Frasure
Industrial Park.
Present: Mayor John O. Cotant, Attorney Tom Holmes, Steve Smart, Jerry Rowland, Merlin
Miller, Ray Griffin, Eric King, Ron Conlin, Jim Phelps and Larry Kohntopp.
Tom Gwinn was present stating he is not here for an approval, but to discuss all requirements that
might be required.
The following was discussed:
1. 10' Landscaping with automatic sprinkling on both streets, (front and back).
2. Screening fence is required.
3. Black top surface.
4. Make traffic as safe as possible.
5. City will want to see a lay out of site plan showing access, etc.
6. Sign permit
7. Tree required every 50'.
8. Address on outside of business has to be clear and readable.
9. Require water supply for Fire Department.
10. Emergency vehicle access.
11. Storm Drain - on site - Required to have a water-oil separator.
12. Required to get a building permit.
13. Lighting.
14. No off street parking.
Mr. Gwinn said he will review the requirements and make a decision.
CITY OF CHUBBUCK, IDAHO
DESIGN REVIEW MEETING APPLICATION
The purpose of this application is to establish a meeting and review time with the City of
Chubbuck Design Review Team consisting of the: Mayor, Building Official, City Planner,
City Engineer, Fire Marshal, Police Chief and other City staff as required. The Design Review
Team meets every Tuesday morning between the hours of 10:30 and 12:00 Noon
This team will work in unison, with you, to establish the criteria for your project as it
relates to the adopted ordinances of the City of Chubbuck. Keep in mind, this is an
informal review and is only conducted on submitted applications. This is a review team
not a design team. Provide (6) six sets of drawings at least one week in advance of your
scheduled meeting. Formal reviews of your plans or project by City staff is conducted
after formal application. Once you make your appointment and it is verified, it is very
important to keep that appointment so others can be scheduled accordingly.
Applicant/Agent:
Telephone Number:
Todd Stinger/Tom Gwinn
(PLEASE PRINT)
208-637-2886
Todd's Automotive
5048 Rainbow Lane
Chubbuck, Id 83202
Todd's Automotive
Frasure h~dustrial Park
Lot//9 and unplatted lot immediately to the east of lot #9
Mailing Address:
Project Title:
Location:
Parcel Number:
Purpose For The Review. Approval of new location and site layout.
Meeting Request Date: 04 / 17 /_ Ol (Tuesdays only)
Alternate Date: __J ~__ (1 1:00 to Noon)
Approved Date: 04 / ~7 / Ol
Approved Time: U:00^M (Notify Applicant)
(Be at permit counter at least 15 minutes prior to your scheduled time)
City Official: L. Kohntopp Date: 04 / o~ /. Ol
10'
~7
N
~7
11
1)- Layout of facilities
2)- Dimensions of building
3)- Dimensions of parking lot
(See Drawing-Diagram)
70X100 (See Drawing-Diagram)
130X170 (See Drawing-Diagram)
Minus the space of 2O ft per corner for grass and graveL
4)- Place and positions of oil separator. * Under concrete floor of
building-South East corner of building. *
5)- Landscaping-Materials-Location- Grass, shrubs, gravel. In the corners of
the lot, installed will be 20ft. of dished grass with a gravel bottom for drainage.
this may include small trees and shrubs in this area also.
6)- Permanent existing tress
(NONE)
7)- Ground treatment..
Fully landscaped
8)- Off street parking and circulation~ Large lot to park-lighted area-drive
through scheme. (See drawing).
9)- Location and sizes of adjacent streets- NORTH arrow and property line.
lO)-Drawings of major exterior elevat¥ons-showing building materials &
proposed color scheme. Existing grade and proposed grade.
11)-Entrances & Exits for drive and pedestrian walkways. (See drawing plans)
See #S for parking. Pedestrian travel-full sidewalk in front and rear of
property.
12)-Lighting and off street parking. Installed will be 102eloodlights off of
buildinb 2 in the front, 3 on the left side, 2 on the rear, 3 on the right side.
13)-Location of building #
_ Rainbow Rd. Chubbuck, Id 83202.
14)-Color of building. (Green & Tan) (Blue & Gray) Brick Waynescoat 4ft.
15)-Size of building.
(70Xl O0)
16)-Height of building. 14ft. walls with a 112 pitch roof.
17)-Lighting and landscaping of outdoor advertising signs. Sign on front of
building-comparable to our current sign.
18)-Location, height & materials of walls-fences-hedges. Fencing will beg~n
at the front corner of the building, follow the property line completely around to
front of building. The face od~ the building will be the only piece not fenced in.
8ft. fence with bob-wire top, included white picket enclosure.
*Note*
They will screen plantings and fixtures to ensure harmony with adjacent
developments or to conceal storage areas, utility installations or other unsightly
development.
20)-Planting of ground cover or surfacing to prevent dust and or erosion.
Property will be completely surfaced with either blacktop or grass.
21)-Area openings-breaks in fencing on street line.
22)-Pitch of roof. (112 pitch)
23)-Arrangement of structures on the parcel.
24)-Drainage-proposed arrangement.
property.
(See drawing -plans)
(See drawing-plans)
Front and rear. In the four corners of the
BUILDING MATERIALS
1)- Steel Building
2)- Brick Waynes coat 4ft. high.
3)- Tin siding above 4ft. painted. (colors)
4)- 6 inch concrete floor.
5)- 2 Bay doors
6)- 112 Pitch of roof.
1)- Chain link fence 8ft. high.
2)- Bob-wire topping offence.
3)- White picket enclosure.
FENCING